CEI of CR 578 from Suncoast Parkway to US 41 at Ayers Road.
CEI of CR 578 (County Line Road) from Suncoast Parkway to US 41 at Ayers Road.
Contract Time: 860 CALENDAR DAYS
Project #'s: FIN# 257298-56201
Counties: Hernando, US-41
This project starts at the intersection of the Suncoast Parkway and County Line Road (CR 578) and continues east to where the new alignment of CR 578 proceeds northward and a new intersection will be created with Trillium Boulevard.
Construction Cost:$20,155,312.41
County Line Rd. will be realigned to meet the new intersection and properties to the south of County Line Rd. will be accessed by the existing road and a cul-de-sac will be constructed at the end. The new alignment proceeds northward through a preset corridor through the Trillium Community and then turns east to US 41 at the existing intersection with Ayers Road. Project elements include: Milling/resurfacing, new roadway construction drainage including ponds, signalized intersections, sidewalk, driveways, striping including thermoplastic and utilities including 12” and 16” water mains.